Producers Strain To Supply Growing Wind Power Market

Demand for wind turbines is booming with world wide sales hitting record levels.
by Delphine Touitou
Stockholm (AFP) Dec 03, 2006
There is an inexhaustible supply of wind to drive their blades, but materials needed to make wind turbines are limited and the industry fears it will fail to keep pace with growing demand for the clean energy source. "We do whatever we can but it's impossible to increase our (production) capacity overnight," a spokesman for the Danish group Vestas told AFP.

"There is a gap between industrial capacity and demand, and it will take several years before we can fill the gap. Don't expect miracles," Peter Wenzel Kruze added.

Vestas is the world leader in wind turbine manufacturing.

Benefiting from spiralling oil prices and the popularity of green energy sources, wind farms -- mostly on land but also offshore -- have in recent years become an increasingly common sight throughout Europe.

Wind-generated power now accounts for three percent of Europe's electricity requirements, according to the European Wind Energy Agency (EWEA). In Denmark the figure is 20 percent, eight percent in Germany and seven percent in Spain.

EWEA hopes 22 percent of European electricity requirements will be filled by wind power by 2030.

Between 1995 and 2005 the amount of electricity produced using wind power grew on average by 32 percent per year in Europe while the number of wind turbines rose by around 22 percent.

Similar growth in the sector has been recorded in the United States where wind power production expanded by 36 percent in 2005 with the help of federal funding.

A number of countries have announced plans for major wind farm programmes both on land and at sea. The rush to wind power has proved a boon for the industry in the shape of lucrative contracts but it has also caused problems for companies as they struggle to meet multiplying deadlines.

Almost all producers have been affected by the problem for some months, according to a spokeswoman at German energy group REpower.

While there was no immediate impact on the group's results, she conceeded that future production capacity could be reduced if delays in deliveries of wind turbine parts continued.

EWEA, representing 80 percent of the wind power industry, acknowledges that delays in wind turbine deliveries, especially turbine motors, are on the increase, but does not wish to overstate the situation.

"I can not say it's a problem to have very strong demand ... it's quite a normal phenomenom in industry. It takes time for both manufacturers and suppliers to adjust production," EWEA president Christian Kjaer said.

Robert Gleitz, wind product chief at General Electric, explains that current supply problems have not affected major component parts of wind turbines such as blades, plinths or turbine pods.

Gleitz does however say that turbines ordered today would not be delivered until 2008 or possibly 2009.

"The industry is adapting and companies are in the process of reorganising their entire supply chain," EWEA spokeswoman Isabelle Valentiny said.

Firms are encouraging suppliers to greatly increase investment and are seeking more long term strategic framework agreements with suppliers and customers.

"The message is: okay, we believe in this (wind energy), you can invest," Wenzel Kruze said.

EWEA added that the price of wind power has fallen steadily in the last 20 years.

"(Wind energy) technology produces 180 times the amount of electricity that it produced in the 80's. It has matured and can compete with other forms of energy," Valentiny said.

Source: Agence France-Presse

Community
Email This Article
Comment On This Article

Related Links
- Powering The World in the 21st Century at Energy-Daily.com



Memory Foam Mattress Review
Newsletters :: SpaceDaily :: SpaceWar :: TerraDaily :: Energy Daily
XML Feeds :: Space News :: Earth News :: War News :: Solar Energy News


China Prioritizes Hydropower In The West
Beijing (XNA) Dec 01, 2006
China will give priority to hydropower development in western regions with rich water resources, said an official with the National Development and Reform Commission (NDRC). China has finished a national survey of water resources and estimated a potential of 500 million kW of hydropower based on those resources, said Zhang Guobao, NDRC deputy director.







  • Producers Strain To Supply Growing Wind Power Market
  • Isolated Armenia Leads The Way In Using Cleaner Car Fuel
  • China Prioritizes Hydropower In The West
  • Russian, Ukrainian Scientists To Collaborate In Solar Research

  • Thorium Poised To Meet World's Energy Needs
  • Bulgaria Signs Contract With Atomstroyexport To Build Nuclear Plant
  • Dwindling Forests And Resources Force Africa To Mull Nuclear Energy
  • Iran Offers To Share Nuclear Know-How With Algeria

  • Steering Clear Of Icy Skies
  • Increase In Carbon Dioxide Emissions Accelerating
  • Researchers Gaze At Cloud Formations
  • France To Create Coal Tax, Tighten Pollution Measures

  • Report Outlines Funding To Conserve Half Of Massachusetts's Land
  • Trees Reversing Skinhead Earth May Aid Global Climate
  • Danish Christmas Tree Shortage Threatens Prices Across Europe
  • Ancestor of Modern Trees Preserves Record Of Ancient Climate Change

  • Indonesia And Australia Seek Regional Action On Dwindling Fish Stocks
  • ASEAN Endorses Major Initiatives To Boost Regional Rice Production
  • Japan Ready For Cut In Indian Ocean Tuna Catch
  • Wheat Gene May Boost Foods' Nutrient Content

  • 'Hummernator' Schwarzenegger Wants Greener Cars
  • GM Shifts Gears, Makes Push For Electric Cars, More Hybrids
  • EPRI, Argonne To Assess Commercial Viability Of Plug-In Hybrid Electric Vehicles
  • London Blazes Anti-Pollution Trail With Vehicle Congestion Charge

  • Boeing Business Jets Delivers Its 100th Green Airplane
  • A380 Wraps Up Technical Route Proving After a Final Trip Over Both Poles
  • DLR And EUROCONTROL Create Joint Total Airport Management Concept
  • Aviation Industry Alarmed At New EU Emission Rules

  • Could NASA Get To Pluto Faster? Space Expert Says Yes - By Thinking Nuclear
  • NASA plans to send new robot to Jupiter
  • Los Alamos Hopes To Lead New Era Of Nuclear Space Tranportion With Jovian Mission
  • Boeing Selects Leader for Nuclear Space Systems Program

  • The content herein, unless otherwise known to be public domain, are Copyright 1995-2006 - SpaceDaily.AFP and UPI Wire Stories are copyright Agence France-Presse and United Press International. ESA PortalReports are copyright European Space Agency. All NASA sourced material is public domain. Additionalcopyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement,agreement or approval of any opinions, statements or information provided by SpaceDaily on any Web page published or hosted by SpaceDaily. Privacy Statement